Hard1 markMultiple Choice
Task 1: Execute project with the urgency required to deliver business valueProcessAgileRetrospective
PMP · Question 08 · Task 1: Execute project with the urgency required to deliver business value
An agile team is struggling with 'Carryover'—user stories are frequently not completed within the sprint and spill over to the next. This is affecting the predictability of the release. What is the MOST effective action the project manager (acting as Scrum Master) can take?
An agile team is struggling with 'Carryover'—user stories are frequently not completed within the sprint and spill over to the next. This is affecting the predictability of the release. What is the MOST effective action the project manager (acting as Scrum Master) can take?
Answer options:
A.
Extend the sprint duration to allow the team to finish the work.
B.
Assign the unfinished stories to the most senior developer to complete quickly.
C.
Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.
D.
Increase the team's capacity by adding more resources.
How to approach this question
Identify the process improvement mechanism in Agile (Retrospective) and the likely artifacts involved (Definition of Ready).
Full Answer
C.Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.✓ Correct
Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.
Carryover usually indicates stories are too large or not well-defined. The Retrospective is the venue to analyze this, and the Definition of Ready is the control mechanism.
Common mistakes
Trying to 'manage' the problem by changing time (sprint length) or resources rather than fixing the process.
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
Expert