Hard1 markMultiple Choice

PMP · Question 08 · Task 1: Execute project with the urgency required to deliver business value

An agile team is struggling with 'Carryover'—user stories are frequently not completed within the sprint and spill over to the next. This is affecting the predictability of the release. What is the MOST effective action the project manager (acting as Scrum Master) can take?

Answer options:

A.

Extend the sprint duration to allow the team to finish the work.

B.

Assign the unfinished stories to the most senior developer to complete quickly.

C.

Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.

D.

Increase the team's capacity by adding more resources.

How to approach this question

Identify the process improvement mechanism in Agile (Retrospective) and the likely artifacts involved (Definition of Ready).

Full Answer

C.Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.✓ Correct
Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.
Carryover usually indicates stories are too large or not well-defined. The Retrospective is the venue to analyze this, and the Definition of Ready is the control mechanism.

Common mistakes

Trying to 'manage' the problem by changing time (sprint length) or resources rather than fixing the process.

Practice the full PMI PMP Mini Practice Exam 2

20 questions · hints · full answers · grading

More questions from this exam