PMP · Question 20 · Task 7: Plan and manage quality of products/deliverables
Which of the following BEST describes the 'Definition of Done' (DoD) in an agile project?
Answer options:
The acceptance criteria specific to a single user story.
A checklist of quality criteria that every user story must meet to be considered complete.
The final approval from the project sponsor.
The list of features required for the Minimum Viable Product (MVP).