Hard1 markMultiple Choice
PMP · Question 20 · Task 7: Plan and manage quality of products/deliverables
Which of the following BEST describes the 'Definition of Done' (DoD) in an agile project?
Which of the following BEST describes the 'Definition of Done' (DoD) in an agile project?
Answer options:
A.
The acceptance criteria specific to a single user story.
B.
A checklist of quality criteria that every user story must meet to be considered complete.
C.
The final approval from the project sponsor.
D.
The list of features required for the Minimum Viable Product (MVP).
How to approach this question
Distinguish between 'Acceptance Criteria' (Specific to one story) and 'Definition of Done' (General to all stories).
Full Answer
B.A checklist of quality criteria that every user story must meet to be considered complete.✓ Correct
A checklist of quality criteria that every user story must meet to be considered complete.
The DoD is a quality standard (Task 7) ensuring that 'Done' means the same thing for every item, preventing technical debt.
Common mistakes
Confusing DoD with Acceptance Criteria.
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
Expert