    PracticePMI PMP®PMI PMP Mini Practice Exam 3Question 5
    Hard1 markMultiple Choice
    Task 5: Ensure team members/stakeholders are adequately trainedPeopleTrainingAgile

    PMP · Question 5 · Task 5: Ensure team members/stakeholders are adequately trained

    A project team is transitioning from predictive to agile. During the first sprint, the PM notices the team is struggling to break down user stories and estimate points effectively. The budget for formal training was cut. What should the PM do?

    Answer options:

    A.

    Switch back to predictive planning for this phase to ensure delivery.

    B.

    Organize internal knowledge-sharing sessions and pair experienced agile practitioners with novices.

    C.

    Request a budget exception from the sponsor, delaying the project until training is approved.

    D.

    Perform the estimation and breakdown for the team until they learn by watching.

    How to approach this question

    Identify a solution that is proactive, cost-effective, and promotes team growth.

    Full Answer

    B.Organize internal knowledge-sharing sessions and pair experienced agile practitioners with novices.✓ Correct
    Leveraging internal expertise (mentoring/pairing) is a key agile practice for continuous improvement and training.

    Common mistakes

    Thinking the PM should do the work (D) or that formal training is the only option (C).
    Question 4All questionsQuestion 6

    Practice the full PMI PMP Mini Practice Exam 3

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ6A project manager is building a team for a high-stakes project. The functional managers have offe...Hard
    View all 20 questions →