Hard1 markMultiple Choice
PMP · Question 6 · Task 6: Build a team
A project manager is building a team for a high-stakes project. The functional managers have offered resources who are available but lack the specific niche skills required. The project has a strict deadline. What is the BEST course of action?
A project manager is building a team for a high-stakes project. The functional managers have offered resources who are available but lack the specific niche skills required. The project has a strict deadline. What is the BEST course of action?
Answer options:
A.
Accept the resources and plan for significant overtime to compensate for the learning curve.
B.
Reject the internal resources and immediately hire external contractors.
C.
Negotiate with functional managers for the required skills or propose a hybrid team of internal staff and external experts.
D.
Adjust the project scope to align with the current team's capabilities.
How to approach this question
Balance the constraint (deadline) with the resource reality. Negotiation is key.
Full Answer
C.Negotiate with functional managers for the required skills or propose a hybrid team of internal staff and external experts.✓ Correct
C
Building a team often requires negotiation to ensure the right mix of skills. A hybrid resource approach is a common solution for niche skills.
Common mistakes
Accepting the status quo (A) or changing scope (D) before trying to solve the resource problem.
Practice the full PMI PMP Mini Practice Exam 3
20 questions · hints · full answers · grading
More questions from this exam
Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard