    PracticePMI PMP®PMI PMP Mini Practice Exam 3Question 1
    Hard1 markMultiple Choice
    Task 1: Manage conflictPeopleConflictAgile

    PMP · Question 1 · Task 1: Manage conflict

    A project manager is leading a hybrid project with a distributed team. During a virtual sprint retrospective, two senior developers begin arguing about the architectural approach for the next release. One insists on a refactor to reduce technical debt, while the other argues for a quick patch to meet the deadline. The argument escalates, and other team members disengage. What should the project manager do FIRST?

    Answer options:

    A.

    Intervene immediately and make a decision based on the project schedule constraints to end the conflict.

    B.

    Remind the team of the ground rules regarding respectful communication and facilitate a collaborative session to evaluate both options.

    C.

    End the meeting early and schedule separate one-on-one meetings with each developer to hear their grievances.

    D.

    Report the behavioral issue to the functional managers of the developers for disciplinary action.

    How to approach this question

    Identify the conflict stage and apply the servant leadership principle of facilitation.

    Full Answer

    B.Remind the team of the ground rules regarding respectful communication and facilitate a collaborative session to evaluate both options.✓ Correct
    B
    In a hybrid/agile environment, the PM acts as a servant leader. Re-establishing ground rules addresses the 'how' of the interaction, while facilitating a technical discussion addresses the 'what'.

    Common mistakes

    Choosing to dictate the solution (A) to save time, which violates agile principles.
    All questionsQuestion 2

    Practice the full PMI PMP Mini Practice Exam 3

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...HardQ6A project manager is building a team for a high-stakes project. The functional managers have offe...Hard