    PracticePMI PMP®PMI PMP Practice Exam 3Question 07
    Hard1 markMultiple Choice
    Task 11: Engage and support virtual teamsvirtual teamscultural awarenessteam engagementcommunication

    PMP · Question 07 · Task 11: Engage and support virtual teams

    A project manager is leading a distributed team across three time zones. During virtual daily stand-ups, they notice that team members in the Asia-Pacific region rarely speak up or ask questions, while team members in North America dominate the conversations. What should the project manager do to improve virtual team engagement?

    Answer options:

    A.

    Schedule separate stand-ups for each time zone to reduce cultural barriers

    B.

    Implement a round-robin format where each team member must provide an update

    C.

    Create multiple communication channels and rotate meeting times to accommodate different cultural communication preferences

    D.

    Ask the Asia-Pacific team members directly why they don't participate more

    How to approach this question

    Consider cultural communication differences and time zone equity. Look for solutions that provide multiple ways to engage rather than forcing uniform participation.

    Full Answer

    C.Create multiple communication channels and rotate meeting times to accommodate different cultural communication preferences✓ Correct
    Virtual team engagement requires understanding cultural communication preferences and ensuring equitable participation opportunities across time zones.

    Common mistakes

    Assuming all team members communicate the same way or that forcing participation will solve engagement issues. Cultural sensitivity is key.
    Question 06All questionsQuestion 08

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →