PMP · Question 01 · Task 1: Manage conflict
During a sprint retrospective in an agile project, two senior developers engage in a heated argument about the technical architecture decisions made during the sprint. The disagreement is becoming personal, with each developer questioning the other's competence. The rest of the team is becoming uncomfortable and disengaged. What should the project manager do FIRST?
During a sprint retrospective in an agile project, two senior developers engage in a heated argument about the technical architecture decisions made during the sprint. The disagreement is becoming personal, with each developer questioning the other's competence. The rest of the team is becoming uncomfortable and disengaged. What should the project manager do FIRST?
Answer options:
Immediately end the retrospective and schedule individual meetings with each developer
Facilitate a structured discussion to help both developers focus on the technical issues rather than personal attacks
Ask the team to vote on which technical approach is better to resolve the conflict quickly
Escalate the conflict to the functional managers of both developers
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 4
90 questions · hints · full answers · grading
Expert