PMP · Question 04 · Task 4: Empower team members and stakeholders
A cross-functional agile team has been working together for six months and has developed strong technical skills. The project manager wants to increase the team's autonomy and decision-making authority for the next phase of the project, which involves more complex technical decisions and stakeholder interactions. What should the project manager do FIRST?
Answer options:
Assess the team's readiness for increased autonomy by evaluating their decision-making track record and stakeholder management skills
Immediately delegate all technical decisions to the team to demonstrate trust and empowerment
Create detailed procedures and guidelines for the team to follow when making decisions
Ask the team to vote on which decisions they want to take responsibility for
90 questions · hints · full answers · grading