PMP · Question 02 · Task 2: Lead a team
A project manager is leading a hybrid software development project with a distributed team across three time zones. The team has been struggling with communication gaps, missed dependencies, and declining velocity over the past two sprints. Team members report feeling disconnected and unclear about priorities. What should the project manager do FIRST to address these issues?
Answer options:
Implement daily status reports from each team member to improve visibility
Mandate that all team members work during overlapping hours to improve collaboration
Facilitate a team workshop to establish communication protocols and shared understanding of priorities
Replace the distributed team structure with a co-located team to eliminate communication issues