Hard1 markMultiple Choice
Task 5: Ensure team members/stakeholders are adequately trainedtrainingagile transitionchange managementskill development

PMP · Question 05 · Task 5: Ensure team members/stakeholders are adequately trained

A project team is transitioning from a predictive to an agile approach mid-project due to changing requirements. Several team members have expressed anxiety about the new methodology and lack confidence in agile practices. The project manager has identified specific training needs around user story writing, estimation techniques, and retrospective facilitation. What should the project manager do FIRST?

Answer options:

A.

Enroll all team members in a comprehensive agile certification program

B.

Hire an external agile coach to work with the team for the remainder of the project

C.

Organize targeted, hands-on workshops focused on the specific agile practices the team needs for immediate project success

D.

Provide online training resources and ask team members to complete them in their spare time

How to approach this question

Look for training approaches that address immediate needs, build confidence, and focus on practical application of required skills.

Full Answer

C.Organize targeted, hands-on workshops focused on the specific agile practices the team needs for immediate project success✓ Correct
C
Effective training for methodology transitions requires targeted, practical approaches that build confidence and address immediate project needs while reducing anxiety.

Common mistakes

Students often choose comprehensive or generic training approaches rather than recognizing the need for targeted, immediate skill development.

Practice the full PMI PMP Practice Exam 4

90 questions · hints · full answers · grading

More questions from this exam