Hard1 markMultiple Choice
PMP · Question 51 · Task 4: Support organizational change
A project manager is rolling out a new process. The team has been trained (Knowledge) and has the tools (Ability), but they revert to the old process whenever the project manager is not watching.<br/><br/>Which ADKAR element is missing?
A project manager is rolling out a new process. The team has been trained (Knowledge) and has the tools (Ability), but they revert to the old process whenever the project manager is not watching.<br/><br/>Which ADKAR element is missing?
Answer options:
A.
Awareness
B.
Knowledge
C.
Ability
D.
Reinforcement
How to approach this question
If they *can* do it but *don't* stick to it, it's a Reinforcement issue.
Full Answer
D.Reinforcement✓ Correct
D
Reinforcement (the R in ADKAR) is about sustaining the change. If people revert to old ways, it means the new way hasn't been reinforced through rewards, recognition, or consequences.
Common mistakes
Thinking it's Desire (maybe, but 'reverting when not watched' strongly suggests lack of reinforcement/habit formation).
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert