PMP · Question 52 · Task 4: Support organizational change
A project will centralize the procurement function of the organization, resulting in the dissolution of local purchasing teams. <br/><br/>What is the PRIMARY responsibility of the project manager regarding this organizational impact?
Answer options:
To hide the impact until the project is completed.
To evaluate the impact of the project on the organization and determine required actions (e.g., transition plans).
To prevent the dissolution of the local teams.
To offer severance packages to the affected employees.