Hard1 markMultiple Choice
PMP · Question 53 · Task 4: Support organizational change
A project manager is planning a global project with teams in Japan, Germany, and Brazil. <br/><br/>Which TWO cultural dimensions should the project manager consider to support effective organizational change across these regions? (Select TWO)
A project manager is planning a global project with teams in Japan, Germany, and Brazil. <br/><br/>Which TWO cultural dimensions should the project manager consider to support effective organizational change across these regions? (Select TWO)
Answer options:
A.
Weather patterns
B.
Time zone differences
C.
Power Distance (hierarchy acceptance)
D.
Internet bandwidth availability
E.
Individualism vs. Collectivism
F.
Currency exchange rates
How to approach this question
Identify 'Cultural' factors (Hofstede's dimensions).
Full Answer
C, E
Power Distance and Individualism are core cultural dimensions that affect how change is received. In high power distance cultures, change needs to come from the top. In collectivist cultures, change needs group consensus.
Common mistakes
Confusing logistical factors (Time zones) with cultural ones.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard