    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 54
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4Agile

    PMP · Question 54 · Task 4: Support organizational change

    An organization is transitioning from Predictive to Agile. The project manager notices that the team is still waiting for detailed instructions before starting work, causing delays.<br/><br/>What is the BEST action to support this cultural shift?

    Answer options:

    A.

    Provide detailed instructions to keep the project moving.

    B.

    Coach the team on self-organization and empower them to make decisions.

    C.

    Report the team to management for insubordination.

    D.

    Switch back to Predictive methodology.

    How to approach this question

    Agile Transformation = Coaching + Empowerment. Don't revert to command-and-control.

    Full Answer

    B.Coach the team on self-organization and empower them to make decisions.✓ Correct
    The PM must support the organizational change (Agile transformation). This requires coaching the team to adopt new behaviors (self-organization). Providing instructions (A) solves the immediate problem but fails the strategic goal of transformation.

    Common mistakes

    Choosing the 'fix it now' option (A) instead of the 'teach them' option (B).
    Question 53All questionsQuestion 55

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →