PMP · Question 54 · Task 4: Support organizational change
An organization is transitioning from Predictive to Agile. The project manager notices that the team is still waiting for detailed instructions before starting work, causing delays.<br/><br/>What is the BEST action to support this cultural shift?
Answer options:
Provide detailed instructions to keep the project moving.
Coach the team on self-organization and empower them to make decisions.
Report the team to management for insubordination.
Switch back to Predictive methodology.