Hard1 markMultiple Choice
PMP · Question 14 · Task 4: Engage stakeholders
Which of the following documents is the PRIMARY source for identifying project stakeholders?
Which of the following documents is the PRIMARY source for identifying project stakeholders?
Answer options:
A.
Stakeholder Engagement Plan
B.
Project Charter
C.
Communications Management Plan
D.
Issue Log
How to approach this question
Think chronologically. What document exists FIRST?
Full Answer
B.Project Charter✓ Correct
Project Charter
The Project Charter authorizes the project and identifies the key stakeholders (Sponsor, Customers) at a high level.
Common mistakes
Selecting the Stakeholder Register (which is the output, not the source) or the Plan.
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
Expert