Hard1 markMultiple Choice
Task 4: Engage stakeholdersProcessStakeholder ManagementInitiation

PMP · Question 14 · Task 4: Engage stakeholders

Which of the following documents is the PRIMARY source for identifying project stakeholders?

Answer options:

A.

Stakeholder Engagement Plan

B.

Project Charter

C.

Communications Management Plan

D.

Issue Log

How to approach this question

Think chronologically. What document exists FIRST?

Full Answer

B.Project Charter✓ Correct
Project Charter
The Project Charter authorizes the project and identifies the key stakeholders (Sponsor, Customers) at a high level.

Common mistakes

Selecting the Stakeholder Register (which is the output, not the source) or the Plan.

Practice the full PMI PMP Mini Practice Exam 2