    Task 4: Engage stakeholdersProcessStakeholder ManagementInitiation

    PMP · Question 14 · Task 4: Engage stakeholders

    Which of the following documents is the PRIMARY source for identifying project stakeholders?

    Answer options:

    A.

    Stakeholder Engagement Plan

    B.

    Project Charter

    C.

    Communications Management Plan

    D.

    Issue Log

    How to approach this question

    Think chronologically. What document exists FIRST?

    Full Answer

    B.Project Charter✓ Correct
    The Project Charter authorizes the project and identifies the key stakeholders (Sponsor, Customers) at a high level.

    Common mistakes

    Selecting the Stakeholder Register (which is the output, not the source) or the Plan.
    Question 13All questionsQuestion 15

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
    View all 20 questions →