For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 16
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesProcessIntegrationHybrid

    PMP · Question 16 · Task 9: Integrate project planning activities

    In a hybrid project, the hardware team uses a predictive waterfall approach, while the software team uses Scrum. The hardware team is delayed by two weeks. This delay will prevent the software team from testing their code on the actual devices during the current sprint. What should the project manager do?

    Answer options:

    A.

    Pause the software team's sprint until the hardware is ready.

    B.

    Force the hardware team to crash the schedule to meet the date.

    C.

    Work with the software team to use simulators or mocks for testing in the current sprint.

    D.

    Extend the software sprint by two weeks to align with the hardware.

    How to approach this question

    In dependency conflicts, look for 'Decoupling' strategies (mocks, stubs, simulators) rather than 'Waiting' strategies.

    Full Answer

    C.Work with the software team to use simulators or mocks for testing in the current sprint.✓ Correct
    Work with the software team to use simulators or mocks for testing in the current sprint.
    Integration management (Task 9) in hybrid involves managing dependencies. Using mocks allows the software team to maintain velocity despite hardware delays.

    Common mistakes

    Pausing the agile team (A) or breaking the timebox (D).
    Question 15All questionsQuestion 17

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
    View all 20 questions →