Hard1 markMultiple Choice
PMP · Question 17 · Task 17: Plan and manage project/phase closure or transitions
A project manager is closing a project. The deliverables have been accepted by the customer, and the final report is written. What is the FINAL activity the project manager must ensure is completed?
A project manager is closing a project. The deliverables have been accepted by the customer, and the final report is written. What is the FINAL activity the project manager must ensure is completed?
Answer options:
A.
Update the lessons learned register.
B.
Release project resources.
C.
Archive project documents.
D.
Celebrate success.
How to approach this question
Think of the absolute end. Once resources are gone, no work can happen.
Full Answer
B.Release project resources.✓ Correct
Releasing resources is the final administrative step. Lessons learned, archiving, and celebrations require the team to be present.
Common mistakes
Thinking Lessons Learned is last (it's done during closure, but before the team leaves).
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
Expert