Hard1 markMultiple Choice

PMP · Question 17 · Task 17: Plan and manage project/phase closure or transitions

A project manager is closing a project. The deliverables have been accepted by the customer, and the final report is written. What is the FINAL activity the project manager must ensure is completed?

Answer options:

A.

Update the lessons learned register.

B.

Release project resources.

C.

Archive project documents.

D.

Celebrate success.

How to approach this question

Think of the absolute end. Once resources are gone, no work can happen.

Full Answer

B.Release project resources.✓ Correct
Releasing resources is the final administrative step. Lessons learned, archiving, and celebrations require the team to be present.

Common mistakes

Thinking Lessons Learned is last (it's done during closure, but before the team leaves).

Practice the full PMI PMP Mini Practice Exam 2

20 questions · hints · full answers · grading

More questions from this exam