    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 18
    Hard1 markShort Answer
    Task 6: Plan and manage scheduleProcessScheduleEstimation

    PMP · Question 18 · Task 6: Plan and manage schedule

    In a project using the Three-Point Estimating technique (Beta/PERT distribution), a task has an Optimistic estimate of 2 days, a Most Likely estimate of 5 days, and a Pessimistic estimate of 14 days. What is the Expected Duration? (Enter the number only).

    How to approach this question

    Use the formula (O + 4M + P) / 6.

    Full Answer

    PERT Formula: (O + 4M + P) / 6<br/>(2 + 20 + 14) / 6 = 36 / 6 = 6 days.

    Common mistakes

    Using the Triangular distribution formula (O+M+P)/3 which would give 7.
    Question 17All questionsQuestion 19

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
    View all 20 questions →