PMP · Question 18 · Task 6: Plan and manage schedule
In a project using the Three-Point Estimating technique (Beta/PERT distribution), a task has an Optimistic estimate of 2 days, a Most Likely estimate of 5 days, and a Pessimistic estimate of 14 days. What is the Expected Duration? (Enter the number only).
In a project using the Three-Point Estimating technique (Beta/PERT distribution), a task has an Optimistic estimate of 2 days, a Most Likely estimate of 5 days, and a Pessimistic estimate of 14 days. What is the Expected Duration? (Enter the number only).
How to approach this question
Use the formula (O + 4M + P) / 6.
Full Answer
6
PERT Formula: (O + 4M + P) / 6<br/>(2 + 20 + 14) / 6 = 36 / 6 = 6 days.
Common mistakes
Using the Triangular distribution formula (O+M+P)/3 which would give 7.
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
Expert