    PracticePMI PMP®TopicsDomain: ProcessTask 6: Plan and manage schedule
    Domain: Process

    Task 6: Plan and manage schedule

    18 questions across 5 exams

    Other subtopics in Domain: Process
    Task 1: Execute project with the urgency required to deliver business value5qTask 1: Execute project with urgency5qTask 10: Manage project changes8qTask 11: Plan and manage procurement7qTask 12: Manage project artifacts5qTask 13: Determine appropriate project methodology4qTask 13: Determine appropriate project methodology/methods and practices5qTask 14: Establish project governance structure5qTask 15: Manage project issues5qTask 16: Ensure knowledge transfer4qTask 16: Ensure knowledge transfer for project continuity3qTask 17: Plan and manage project closure3qTask 17: Plan and manage project transitions1qTask 17: Plan and manage project/phase closure or transitions4qTask 2: Manage communications6qTask 3: Assess and manage risks11qTask 4: Engage stakeholders9qTask 5: Plan and manage budget2qTask 5: Plan and manage budget and resources11qTask 7: Plan and manage quality7qTask 7: Plan and manage quality of products/deliverables4qTask 8: Plan and manage scope11qTask 9: Integrate project planning activities9q

    Covered in these exams

    PMI PMP Practice ExamPMP Process Domain Practice ExamPMI PMP Mini Practice ExamPMI PMP Mini Practice Exam 2PMI PMP Mini Practice Exam 3

    All questions (18)

    Q16Hard1 mark·PMI PMP Practice Exam

    A project manager is planning a project with a high degree of uncertainty regarding the final product design. The stakeholders are highly involved and want to see progress frequently. Which scheduling method is MOST appropriate?

    Worked answer available with free account
    View question →
    Q22Hard1 mark·PMI PMP Practice Exam

    An agile team is consistently failing to meet their sprint commitment. They commit to 40 story points but only deliver 25. This has happened for three sprints. What should the project manager (acting as Scrum Master) do?

    Worked answer available with free account
    View question →
    Q26Medium1 mark·PMI PMP Practice Exam

    A project has a critical path of A-B-C-D. Task A is 3 days, B is 4 days, C is 5 days, D is 2 days. The project manager decides to 'crash' the project by reducing Task C by 2 days at a cost of $1000. What is the new duration of the critical path? (Enter number only)

    Worked answer available with free account
    View question →
    Q47Hard1 mark·PMI PMP Practice Exam

    A project manager is leading an agile team. The team is complaining that the daily standup is taking 30 minutes instead of 15. What is the MOST likely cause?

    Worked answer available with free account
    View question →
    Q55Hard1 mark·PMI PMP Practice Exam

    A project manager is leading a project with a team that is new to Agile. The team is struggling to estimate stories using Story Points. They keep trying to equate points to hours. What should the PM do?

    Worked answer available with free account
    View question →
    Q74Medium1 mark·PMI PMP Practice Exam

    A project manager is leading a team that uses 'Planning Poker'. What is the main benefit of this technique?

    Worked answer available with free account
    View question →
    Q86Medium1 mark·PMI PMP Practice Exam

    A project manager is leading a project to build a new stadium. The project is using a predictive lifecycle. The steel beams are delayed by 4 weeks due to a strike. This activity is on the critical path. What is the impact on the project finish date?

    Worked answer available with free account
    View question →
    Q88Hard1 mark·PMI PMP Practice Exam

    A project manager is leading a project to develop a new video game. The team is using Agile. The marketing team needs a firm release date for the ad campaign. The team says, 'We will be done when we are done.' What should the PM do?

    Worked answer available with free account
    View question →
    Q103Medium1 mark·PMI PMP Practice Exam

    A project manager is leading a project to build a new factory. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM calculates the Schedule Variance (SV). SV = EV - PV. The SV is -$10,000. What does this mean?

    Worked answer available with free account
    View question →
    Q109Medium1 mark·PMI PMP Practice Exam

    A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM uses 'Fast Tracking'. What is this?

    Worked answer available with free account
    View question →
    Q111Medium1 mark·PMI PMP Practice Exam

    A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM uses 'Crashing'. What is this?

    Worked answer available with free account
    View question →
    Q20Hard1 mark·PMP Process Domain Practice Exam

    Activity A has a duration of 5 days. Its Early Start (ES) is day 3 and Early Finish (EF) is day 8. Its Late Start (LS) is day 10 and Late Finish (LF) is day 15. What is the Total Float for Activity A? (Enter the number only)

    Worked answer available with free account
    View question →
    Q21Hard1 mark·PMP Process Domain Practice Exam

    A project is behind schedule. The Critical Path is A-C-E (20 days). Path B-D-E is 18 days. The project manager decides to crash Activity C by 3 days. What is the new project duration?

    Worked answer available with free account
    View question →
    Q22Hard1 mark·PMP Process Domain Practice Exam

    An agile team has a velocity of 20 story points per sprint. The release backlog has 100 points remaining. The Product Owner adds a new feature estimated at 10 points. How many sprints are now required to complete the release?

    Worked answer available with free account
    View question →
    Q23Hard1 mark·PMP Process Domain Practice Exam

    A project is delayed. The project manager needs to compress the schedule without changing the scope. Which two techniques can be used? (Select TWO)

    Worked answer available with free account
    View question →
    Q018Hard1 mark·PMI PMP Mini Practice Exam

    A project has the following activity duration estimates: Activity A (Optimistic: 3, Most Likely: 5, Pessimistic: 13). Using the Beta (PERT) distribution, what is the expected duration for Activity A? (Enter the number only).

    Worked answer available with free account
    View question →
    Q18Hard1 mark·PMI PMP Mini Practice Exam 2

    In a project using the Three-Point Estimating technique (Beta/PERT distribution), a task has an Optimistic estimate of 2 days, a Most Likely estimate of 5 days, and a Pessimistic estimate of 14 days. What is the Expected Duration? (Enter the number only).

    Worked answer available with free account
    View question →
    Q20Hard1 mark·PMI PMP Mini Practice Exam 3

    A project is using a hybrid approach. The hardware components follow a predictive schedule, while software is agile. The hardware delivery is delayed by 2 weeks due to supply chain issues. This hardware is required for the software team's integration testing in the current sprint. What should the PM do?

    Worked answer available with free account
    View question →