Hard1 markMultiple Choice
PMP · Question 21 · Task 6: Plan and manage schedule
A project is behind schedule. The Critical Path is A-C-E (20 days). Path B-D-E is 18 days. The project manager decides to crash Activity C by 3 days. What is the new project duration?
A project is behind schedule. The Critical Path is A-C-E (20 days). Path B-D-E is 18 days. The project manager decides to crash Activity C by 3 days. What is the new project duration?
Answer options:
A.
17 days
B.
18 days
C.
20 days
D.
15 days
How to approach this question
Check if the critical path shifts. Reduce the crashed path, then compare all paths to find the new longest path.
Full Answer
B.18 days✓ Correct
B
Task 6 involves modifying the schedule. Crashing reduces the duration of one path, but the project duration is determined by the *longest* path. Path 2 (18 days) prevents the project from finishing in 17 days.
Common mistakes
Ignoring the secondary path and assuming the project shortens by the full crash amount.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert