Hard1 markMultiple Choice

PMP · Question 03 · Task 1: Execute project with the urgency required to deliver business value

During a predictive construction project, the client requests a change to the interior design materials to use a newer, more sustainable composite. This material was not available during the planning phase. The change will increase material costs by 10% but reduce long-term maintenance costs by 40% for the client. The project is currently on budget. What is the BEST course of action for the project manager?

Answer options:

A.

Reject the change as it increases the project budget and deviates from the baseline.

B.

Implement the change immediately using the management reserve to cover the cost increase.

C.

Process a change request detailing the implementation cost increase and the lifecycle value benefit.

D.

Ask the client to pay for the material difference directly to the supplier to avoid changing the project budget.

How to approach this question

Identify the option that balances process (change control) with value delivery (lifecycle benefits).

Full Answer

C.Process a change request detailing the implementation cost increase and the lifecycle value benefit.✓ Correct
C
The PM must execute with urgency to deliver value. Recognizing the long-term value of the sustainable material is key, but in a predictive environment, this must be handled through integrated change control.

Common mistakes

A is a common 'traditional' PM answer that fails the value test. B ignores governance.