    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 04
    Hard1 markMultiple Choice
    Task 1: Execute project with the urgency required to deliver business valueTask 1AgileArtifacts

    PMP · Question 04 · Task 1: Execute project with the urgency required to deliver business value

    A project manager is leading a team to develop a new mobile application. The market is highly volatile. The sponsor wants to ensure the team delivers the highest value features first. Which artifact should the project manager primarily rely on to facilitate this?

    Answer options:

    A.

    The Project Charter

    B.

    The Product Backlog

    C.

    The Work Breakdown Structure (WBS)

    D.

    The Benefits Management Plan

    How to approach this question

    Associate 'highest value features first' and 'volatile market' with Agile/Adaptive artifacts.

    Full Answer

    B.The Product Backlog✓ Correct
    B
    In an agile/adaptive context (implied by 'volatile market'), the Product Backlog is the tool used to subdivide tasks and prioritize them to deliver value incrementally.

    Common mistakes

    Confusing the strategic Benefits Management Plan with the tactical Product Backlog.
    Question 03All questionsQuestion 05

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...HardQ06A project manager takes over a project that is halfway through execution. Stakeholders are compla...Hard
    View all 60 questions →