Hard1 markMultiple Choice
Task 2: Manage communicationsTask 2Virtual TeamsCommunication

PMP · Question 05 · Task 2: Manage communications

A global project team is facing difficulties with communication due to time zone differences. Critical decisions are being delayed because emails are not answered promptly. The project manager needs to improve the communication method. What is the BEST approach?

Answer options:

A.

Mandate a daily stand-up meeting at a time that is convenient for the head office.

B.

Implement a 'follow-the-sun' workflow where work is handed off at the end of each day.

C.

Establish a core set of 'overlap hours' for synchronous communication and use asynchronous tools for status updates.

D.

Route all communications through the project manager to ensure nothing is missed.

How to approach this question

Look for the option that balances the constraints (time zones) with the need (decision making).

Full Answer

C.Establish a core set of 'overlap hours' for synchronous communication and use asynchronous tools for status updates.✓ Correct
C
Task 2 involves determining communication methods. Overlap hours allow for real-time problem solving (high bandwidth), while asynchronous tools handle routine info (low bandwidth), optimizing the process.

Common mistakes

Choosing A is a common 'command and control' mistake. B is a specific workflow strategy, not a communication strategy.