PMP · Question 20 · Task 6: Plan and manage schedule
Activity A has a duration of 5 days. Its Early Start (ES) is day 3 and Early Finish (EF) is day 8. Its Late Start (LS) is day 10 and Late Finish (LF) is day 15. What is the Total Float for Activity A? (Enter the number only)
Activity A has a duration of 5 days. Its Early Start (ES) is day 3 and Early Finish (EF) is day 8. Its Late Start (LS) is day 10 and Late Finish (LF) is day 15. What is the Total Float for Activity A? (Enter the number only)
How to approach this question
Calculate Float = LS - ES or LF - EF.
Full Answer
7
Total Float = LS - ES = 10 - 3 = 7. Alternatively, LF - EF = 15 - 8 = 7.
Common mistakes
Subtracting Duration from LS instead of ES.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert