    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 20
    Hard1 markShort Answer
    Task 6: Plan and manage scheduleTask 6CalculationSchedule

    PMP · Question 20 · Task 6: Plan and manage schedule

    Activity A has a duration of 5 days. Its Early Start (ES) is day 3 and Early Finish (EF) is day 8. Its Late Start (LS) is day 10 and Late Finish (LF) is day 15. What is the Total Float for Activity A? (Enter the number only)

    How to approach this question

    Calculate Float = LS - ES or LF - EF.

    Full Answer

    Total Float = LS - ES = 10 - 3 = 7. Alternatively, LF - EF = 15 - 8 = 7.

    Common mistakes

    Subtracting Duration from LS instead of ES.
    Question 19All questionsQuestion 21

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →