Hard1 markShort Answer
Task 6: Plan and manage scheduleTask 6CalculationSchedule

PMP · Question 20 · Task 6: Plan and manage schedule

Activity A has a duration of 5 days. Its Early Start (ES) is day 3 and Early Finish (EF) is day 8. Its Late Start (LS) is day 10 and Late Finish (LF) is day 15. What is the Total Float for Activity A? (Enter the number only)

How to approach this question

Calculate Float = LS - ES or LF - EF.

Full Answer

7
Total Float = LS - ES = 10 - 3 = 7. Alternatively, LF - EF = 15 - 8 = 7.

Common mistakes

Subtracting Duration from LS instead of ES.