Hard1 markMultiple Choice
PMP · Question 22 · Task 6: Plan and manage schedule
An agile team has a velocity of 20 story points per sprint. The release backlog has 100 points remaining. The Product Owner adds a new feature estimated at 10 points. How many sprints are now required to complete the release?
An agile team has a velocity of 20 story points per sprint. The release backlog has 100 points remaining. The Product Owner adds a new feature estimated at 10 points. How many sprints are now required to complete the release?
Answer options:
A.
5 sprints
B.
5.5 sprints
C.
6 sprints
D.
6.5 sprints
How to approach this question
Add new work to total. Divide by velocity. Round up to the nearest whole number.
Full Answer
C.6 sprints✓ Correct
C
Task 6 involves measuring progress. 110 points / 20 points/sprint = 5.5 sprints. You need the 6th sprint to finish the last 10 points.
Common mistakes
Forgetting to add the new scope or failing to round up.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert