Hard1 markMultiple Choice
Task 6: Plan and manage scheduleTask 6AgileCalculation

PMP · Question 22 · Task 6: Plan and manage schedule

An agile team has a velocity of 20 story points per sprint. The release backlog has 100 points remaining. The Product Owner adds a new feature estimated at 10 points. How many sprints are now required to complete the release?

Answer options:

A.

5 sprints

B.

5.5 sprints

C.

6 sprints

D.

6.5 sprints

How to approach this question

Add new work to total. Divide by velocity. Round up to the nearest whole number.

Full Answer

C.6 sprints✓ Correct
C
Task 6 involves measuring progress. 110 points / 20 points/sprint = 5.5 sprints. You need the 6th sprint to finish the last 10 points.

Common mistakes

Forgetting to add the new scope or failing to round up.