PMP · Question 018 · Task 6: Plan and manage schedule
A project has the following activity duration estimates: Activity A (Optimistic: 3, Most Likely: 5, Pessimistic: 13). Using the Beta (PERT) distribution, what is the expected duration for Activity A? (Enter the number only).
20 questions · hints · full answers · grading