PMP · Question 003 · Task 4: Empower team members and stakeholders
A project manager is taking over a project where the team is demotivated due to micromanagement by the previous manager. The project uses a hybrid approach. Which TWO actions should the project manager take to empower the team?
Answer options:
Assign specific tasks to each team member to ensure clarity of roles.
Work with the team to co-create a team charter and ground rules.
Implement a strict reporting schedule to monitor performance improvements.
Increase the frequency of status meetings to provide more guidance.
Delegate decision-making authority for technical solutions to the team members.
Request a bonus for the team to boost morale immediately.