Hard1 markMultiple Choice

PMP · Question 006 · Task 5: Ensure team members are trained

A project manager identifies that a junior team member lacks the specific technical skills required for an upcoming critical task. No other resources are available. What should the project manager do FIRST?

Answer options:

A.

Reassign the task to a senior member of another team.

B.

Pair the junior member with a subject matter expert for mentoring and guidance.

C.

Update the risk register to reflect the potential delay.

D.

Send the team member to an external training course immediately.

How to approach this question

Focus on 'Training' and 'Mentoring' as the solution to skill gaps.

Full Answer

B.Pair the junior member with a subject matter expert for mentoring and guidance.✓ Correct
B
The PM must ensure team members are adequately trained (Task 5). Pairing/Mentoring is an agile and effective way to transfer knowledge immediately on the job.

Common mistakes

Choosing C (Passive documentation) or A (Ignoring constraints).