Hard1 markMultiple Choice
PMP · Question 006 · Task 5: Ensure team members are trained
A project manager identifies that a junior team member lacks the specific technical skills required for an upcoming critical task. No other resources are available. What should the project manager do FIRST?
A project manager identifies that a junior team member lacks the specific technical skills required for an upcoming critical task. No other resources are available. What should the project manager do FIRST?
Answer options:
A.
Reassign the task to a senior member of another team.
B.
Pair the junior member with a subject matter expert for mentoring and guidance.
C.
Update the risk register to reflect the potential delay.
D.
Send the team member to an external training course immediately.
How to approach this question
Focus on 'Training' and 'Mentoring' as the solution to skill gaps.
Full Answer
B.Pair the junior member with a subject matter expert for mentoring and guidance.✓ Correct
B
The PM must ensure team members are adequately trained (Task 5). Pairing/Mentoring is an agile and effective way to transfer knowledge immediately on the job.
Common mistakes
Choosing C (Passive documentation) or A (Ignoring constraints).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert