For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 005
    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementsPeopleNegotiation

    PMP · Question 005 · Task 8: Negotiate project agreements

    During a project negotiation with a vendor, the vendor states they cannot meet the required delivery date without a 20% cost increase. The project budget is fixed, but the schedule has some flexibility. What is the BEST negotiation strategy for the project manager?

    Answer options:

    A.

    Demand the vendor meet the original terms or threaten to cancel the contract.

    B.

    Accept the cost increase and submit a change request for additional budget.

    C.

    Collaborate to trade the schedule flexibility for the fixed cost constraint.

    D.

    Reduce the scope of the deliverable to meet both cost and schedule targets.

    How to approach this question

    Identify the constraints (Fixed Cost) and the flexibility (Schedule). Use the flexible constraint to protect the fixed one.

    Full Answer

    C.Collaborate to trade the schedule flexibility for the fixed cost constraint.✓ Correct
    The PM must analyze the bounds of the negotiation (Task 8). With a fixed budget and flexible schedule, the optimal strategy is to offer more time in exchange for keeping the price flat.

    Common mistakes

    Choosing B (Ignoring constraints) or D (Premature scope reduction).
    Question 004All questionsQuestion 006

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ006A project manager identifies that a junior team member lacks the specific technical skills requir...Hard
    View all 20 questions →