Hard1 markMultiple Choice

PMP · Question 017 · Task 17: Plan and manage project closure

A project manager is closing a project. The deliverables have been accepted, and the final report is written. What is the FINAL step the project manager must take?

Answer options:

A.

Release the project resources.

B.

Archive project documents and update organizational process assets.

C.

Celebrate success with the team.

D.

Release the team and close the project cost codes.

How to approach this question

Closure sequence: Acceptance -> Handover -> Lessons Learned -> Archive -> Release Resources.

Full Answer

D.Release the team and close the project cost codes.✓ Correct
D
Task 17 (Closure). While the order can vary slightly, releasing resources and closing accounts ensures no further work is done or charged. It is the definitive end.

Common mistakes

Confusing the order of archiving vs releasing resources.