    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 017
    Hard1 markMultiple Choice
    Task 17: Plan and manage project closureProcessClosure

    PMP · Question 017 · Task 17: Plan and manage project closure

    A project manager is closing a project. The deliverables have been accepted, and the final report is written. What is the FINAL step the project manager must take?

    Answer options:

    A.

    Release the project resources.

    B.

    Archive project documents and update organizational process assets.

    C.

    Celebrate success with the team.

    D.

    Release the team and close the project cost codes.

    How to approach this question

    Closure sequence: Acceptance -> Handover -> Lessons Learned -> Archive -> Release Resources.

    Full Answer

    D.Release the team and close the project cost codes.✓ Correct
    Task 17 (Closure). While the order can vary slightly, releasing resources and closing accounts ensures no further work is done or charged. It is the definitive end.

    Common mistakes

    Confusing the order of archiving vs releasing resources.
    Question 016All questionsQuestion 018

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →