    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 016
    Hard1 markMultiple Choice
    Task 2: Lead a teamPeopleLeadership Style

    PMP · Question 016 · Task 2: Lead a team

    Which of the following scenarios BEST describes when a project manager should use a 'Servant Leadership' style?

    Answer options:

    A.

    When the team is new, inexperienced, and requires strict direction.

    B.

    When the project is in a crisis and immediate, decisive action is needed.

    C.

    When the team is self-organizing and working in an agile environment.

    D.

    When working with external vendors who have fixed price contracts.

    How to approach this question

    Match 'Agile/Self-organizing' with 'Servant Leadership'.

    Full Answer

    C.When the team is self-organizing and working in an agile environment.✓ Correct
    Task 2 (Lead a team) requires adapting leadership style. Servant leadership is the default for Agile, focusing on removing impediments (Task 7) and empowering the team (Task 4).

    Common mistakes

    Choosing A (Directive is better for total novices) or B (Directive is better for fire-fighting).
    Question 015All questionsQuestion 017

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →