For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 015
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transferProcessKnowledge Management

    PMP · Question 015 · Task 16: Ensure knowledge transfer

    A project manager takes over a project in execution. The project is using a predictive approach. The PM notices that the Lessons Learned Register is empty. What should the PM do?

    Answer options:

    A.

    Wait until the project closure phase to populate the register.

    B.

    Schedule a meeting with the team to identify lessons learned to date and update the register.

    C.

    Fill out the register based on the previous project manager's emails.

    D.

    Ignore the register as the project is already halfway through.

    How to approach this question

    Lessons Learned is a continuous process, not a one-time event.

    Full Answer

    B.Schedule a meeting with the team to identify lessons learned to date and update the register.✓ Correct
    B
    Task 16 (Knowledge Transfer) and Task 12 (Manage Artifacts). The PM must ensure knowledge is captured continuously to improve current performance.

    Common mistakes

    Choosing A (Old school thinking that lessons learned is a closing activity).
    Question 014All questionsQuestion 016

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →