PMP · Question 014 · Task 9: Integrate project planning activities

In a hybrid project, the predictive stream is delayed, which will impact the agile stream's upcoming release. The agile team is frustrated. What should the project manager do FIRST?

Answer options:

A.

Ask the agile team to work overtime to make up for the delay.

B.

Crash the predictive schedule by adding more resources.

C.

Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.

D.

Delay the release date and inform the stakeholders.

How to approach this question

Hybrid issues require Integration. Bring the parts together.

Full Answer

C.Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.✓ Correct
C
In hybrid projects, managing dependencies between streams is critical (Task 9). Facilitating a joint solution empowers the teams and ensures alignment.

Common mistakes

Choosing B (Jumping to a specific schedule compression technique without team input).