For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 014
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesProcessHybridIntegration

    PMP · Question 014 · Task 9: Integrate project planning activities

    In a hybrid project, the predictive stream is delayed, which will impact the agile stream's upcoming release. The agile team is frustrated. What should the project manager do FIRST?

    Answer options:

    A.

    Ask the agile team to work overtime to make up for the delay.

    B.

    Crash the predictive schedule by adding more resources.

    C.

    Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.

    D.

    Delay the release date and inform the stakeholders.

    How to approach this question

    Hybrid issues require Integration. Bring the parts together.

    Full Answer

    C.Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.✓ Correct
    In hybrid projects, managing dependencies between streams is critical (Task 9). Facilitating a joint solution empowers the teams and ensures alignment.

    Common mistakes

    Choosing B (Jumping to a specific schedule compression technique without team input).
    Question 013All questionsQuestion 015

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →