Hard1 markMultiple Choice
PMP · Question 014 · Task 9: Integrate project planning activities
In a hybrid project, the predictive stream is delayed, which will impact the agile stream's upcoming release. The agile team is frustrated. What should the project manager do FIRST?
In a hybrid project, the predictive stream is delayed, which will impact the agile stream's upcoming release. The agile team is frustrated. What should the project manager do FIRST?
Answer options:
A.
Ask the agile team to work overtime to make up for the delay.
B.
Crash the predictive schedule by adding more resources.
C.
Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.
D.
Delay the release date and inform the stakeholders.
How to approach this question
Hybrid issues require Integration. Bring the parts together.
Full Answer
C.Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.✓ Correct
C
In hybrid projects, managing dependencies between streams is critical (Task 9). Facilitating a joint solution empowers the teams and ensures alignment.
Common mistakes
Choosing B (Jumping to a specific schedule compression technique without team input).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert