PMP · Question 014 · Task 9: Integrate project planning activities
In a hybrid project, the predictive stream is delayed, which will impact the agile stream's upcoming release. The agile team is frustrated. What should the project manager do FIRST?
Answer options:
Ask the agile team to work overtime to make up for the delay.
Crash the predictive schedule by adding more resources.
Facilitate a joint meeting between both streams to discuss the impact and re-plan the release.
Delay the release date and inform the stakeholders.