PMP · Question 013 · Task 9: Collaborate with stakeholders
A key stakeholder is refusing to approve the project management plan because they believe the communication strategy is insufficient. The project manager has already explained the plan twice. What should the project manager do NEXT?
A key stakeholder is refusing to approve the project management plan because they believe the communication strategy is insufficient. The project manager has already explained the plan twice. What should the project manager do NEXT?
Answer options:
A.
Proceed with the plan as it was approved by the sponsor.
B.
Ask the stakeholder to specify their communication needs and update the plan to address them.
C.
Escalate the issue to the sponsor to override the stakeholder.
D.
Send the stakeholder a copy of the PMI standards on communication planning.
How to approach this question
If a stakeholder resists, seek to understand their needs (Pull don't Push).
Full Answer
B.Ask the stakeholder to specify their communication needs and update the plan to address them.✓ Correct
B
The PM must collaborate (Task 9) and manage communications (Task 2). Explaining the plan didn't work, so the PM must listen and adapt to the stakeholder's needs.
Common mistakes
Choosing A (ignoring stakeholder) or C (premature escalation).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert