Hard1 markMultiple Choice
Task 4: Engage stakeholdersProcessStakeholder Identification

PMP · Question 019 · Task 4: Engage stakeholders

A project manager is identifying stakeholders for a new hospital construction project. Which TWO actions should the project manager take to ensure comprehensive stakeholder identification?

Answer options:

A.

Wait for stakeholders to contact the project team with their concerns.

B.

Review the lessons learned from previous similar projects.

C.

Only identify stakeholders who have financial authority.

D.

Conduct interviews with the project sponsor and key experts.

E.

Finalize the stakeholder register before the charter is signed.

F.

Exclude opponents of the project to avoid conflict.

How to approach this question

Select TWO. Look for proactive research methods.

Full Answer

B, D
Task 4 (Engage Stakeholders). Identification requires looking at historical data (B) and consulting with experts/leaders (D).

Common mistakes

Choosing E (Thinking it's a one-time task) or F (Avoiding conflict).