PMP · Question 109 · Task 6: Plan and manage schedule
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM uses 'Fast Tracking'. What is this?
Answer options:
Adding resources.
Performing activities in parallel that were originally planned in sequence.
Reducing scope.
Working overtime.