PMP · Question 109 · Task 6: Plan and manage schedule

A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM uses 'Fast Tracking'. What is this?

Answer options:

A.

Adding resources.

B.

Performing activities in parallel that were originally planned in sequence.

C.

Reducing scope.

D.

Working overtime.

How to approach this question

Fast Tracking = Parallel. Crashing = Resources/Money.

Full Answer

B.Performing activities in parallel that were originally planned in sequence.✓ Correct
B
Task 6 (Schedule). Fast Tracking trades Risk for Time. Crashing trades Cost for Time.

Common mistakes

Confusing Fast Tracking with Crashing.