Medium1 markMultiple Choice
PMP · Question 109 · Task 6: Plan and manage schedule
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM uses 'Fast Tracking'. What is this?
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM uses 'Fast Tracking'. What is this?
Answer options:
A.
Adding resources.
B.
Performing activities in parallel that were originally planned in sequence.
C.
Reducing scope.
D.
Working overtime.
How to approach this question
Fast Tracking = Parallel. Crashing = Resources/Money.
Full Answer
B.Performing activities in parallel that were originally planned in sequence.✓ Correct
B
Task 6 (Schedule). Fast Tracking trades Risk for Time. Crashing trades Cost for Time.
Common mistakes
Confusing Fast Tracking with Crashing.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert