    PracticePMI PMP®PMI PMP Practice ExamQuestion 108
    Medium1 markMultiple Choice
    Task 1: Execute project with urgencyBusiness EnvironmentValueAgile

    PMP · Question 108 · Task 1: Execute project with urgency

    A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'Minimum Viable Product' (MVP). What is this?

    Answer options:

    A.

    The final product.

    B.

    The smallest version of the product that can be released to customers to gather feedback and validate hypotheses.

    C.

    A prototype that is thrown away.

    D.

    The beta version.

    How to approach this question

    MVP = Learn.

    Full Answer

    B.The smallest version of the product that can be released to customers to gather feedback and validate hypotheses.✓ Correct
    B
    Task 1 (Value). MVP is a strategy to maximize value by minimizing waste (building the wrong thing). It validates the business case.

    Common mistakes

    Thinking MVP is 'Version 1.0' (it's often smaller) or 'Crappy Product' (it must be viable).
    Question 107All questionsQuestion 109

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →