For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 04
    Hard1 markMultiple Choice
    Task 7: Address and remove impedimentsPeopleImpedimentsMatrix

    PMP · Question 04 · Task 7: Address and remove impediments

    A project team in a matrix organization is struggling. The functional manager keeps pulling key resources away for operational emergencies, causing sprint delays. The project manager has tried discussing this with the functional manager but the behavior continues. What should the project manager do NEXT?

    Answer options:

    A.

    Update the risk register and accept the schedule delays as inevitable.

    B.

    Ask the team to work overtime to make up for the lost hours.

    C.

    Analyze the impact of the resource unavailability on the project critical path/value delivery and present this data to the project sponsor.

    D.

    File a formal complaint against the functional manager with HR.

    How to approach this question

    The PM has already tried direct negotiation (Level 1). The next step is not to give up, but to escalate constructively with data.

    Full Answer

    C.Analyze the impact of the resource unavailability on the project critical path/value delivery and present this data to the project sponsor.✓ Correct
    C
    In a matrix organization, resource availability is a common conflict. If the functional manager doesn't cooperate, the PM must escalate to the sponsor/governance body, armed with impact analysis.

    Common mistakes

    Thinking escalation is always wrong (it's necessary when authority limits are reached) or punishing the team (overtime).
    Question 03All questionsQuestion 05

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...HardQ06During a project, a team member approaches the project manager and admits they lack the skills to...Hard
    View all 114 questions →