Hard1 markMultiple Choice

PMP · Question 06 · Task 5: Ensure team members are trained

During a project, a team member approaches the project manager and admits they lack the skills to complete a assigned technical task, which is on the critical path. What should the project manager do FIRST?

Answer options:

A.

Reassign the task to a more senior team member immediately to protect the schedule.

B.

Send the team member to external training and pause the task until they return.

C.

Note the lack of skills in the team member's performance review.

D.

Pair the team member with a senior expert to complete the task together (Pair Programming/Mentoring).

How to approach this question

Look for the 'win-win'. Protect the project AND grow the person.

Full Answer

D.Pair the team member with a senior expert to complete the task together (Pair Programming/Mentoring).✓ Correct
D
Pairing or mentoring is a key agile and servant leadership technique. It addresses the immediate skill gap without delaying the project significantly and builds long-term capacity.

Common mistakes

Immediately replacing the person (A) or pausing for formal training (B) when on-the-job support is an option.