Hard1 markShort Answer
Task 5: Plan and manage budgetProcessCostCalculation

PMP · Question 07 · Task 5: Plan and manage budget

A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols or commas)

How to approach this question

Calculate EV, then CPI, then EAC using the formula BAC/CPI.

Full Answer

112500
1. EV = 40% * 100,000 = 40,000.<br/>2. CPI = EV / AC = 40,000 / 45,000 = 0.8888...<br/>3. EAC = BAC / CPI = 100,000 / (40,000/45,000) = 100,000 * (45,000/40,000) = 112,500.

Common mistakes

Using the wrong EAC formula (e.g., AC + BAC - EV) which applies when variance is atypical.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam