Hard1 markShort Answer
PMP · Question 07 · Task 5: Plan and manage budget
A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols or commas)
A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols or commas)
How to approach this question
Calculate EV, then CPI, then EAC using the formula BAC/CPI.
Full Answer
112500
1. EV = 40% * 100,000 = 40,000.<br/>2. CPI = EV / AC = 40,000 / 45,000 = 0.8888...<br/>3. EAC = BAC / CPI = 100,000 / (40,000/45,000) = 100,000 * (45,000/40,000) = 112,500.
Common mistakes
Using the wrong EAC formula (e.g., AC + BAC - EV) which applies when variance is atypical.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert