For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 03
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersPeopleStakeholdersAgile

    PMP · Question 03 · Task 9: Collaborate with stakeholders

    A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it does not meet business needs. The Product Owner insists the team followed the acceptance criteria. Which TWO actions should the project manager take?

    Answer options:

    A.

    Defend the team by showing the signed-off user stories to the stakeholder.

    B.

    Facilitate a meeting between the Product Owner and stakeholder to review the product vision and roadmap.

    C.

    Instruct the team to immediately rework the feature based on the stakeholder's verbal feedback.

    D.

    Work with the team to conduct a root cause analysis of why the acceptance criteria did not capture the business need.

    E.

    Request the stakeholder to write detailed requirements documents for future sprints.

    F.

    Escalate the issue to the project sponsor as a scope creep attempt.

    How to approach this question

    Select TWO. Look for actions that build shared understanding (People) and improve the process (Process).

    Full Answer

    The PM needs to bridge the gap between the PO and Stakeholder (Collaboration) and help the team learn why the 'Definition of Done' or criteria failed to match value (Process improvement).

    Common mistakes

    Being defensive (A) or blindly accepting changes without process (C).
    Question 02All questionsQuestion 04

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...HardQ06During a project, a team member approaches the project manager and admits they lack the skills to...Hard
    View all 114 questions →