Hard1 markMultiple Choice
PMP · Question 08 · Task 13: Determine appropriate project methodology
A project manager is leading a project to develop a new medical device. The regulatory requirements are strict and fixed, but the software interface design is uncertain and requires user feedback. Which development approach is MOST appropriate?
A project manager is leading a project to develop a new medical device. The regulatory requirements are strict and fixed, but the software interface design is uncertain and requires user feedback. Which development approach is MOST appropriate?
Answer options:
A.
Predictive approach for the entire project to ensure compliance.
B.
Agile approach for the entire project to maximize adaptability.
C.
Hybrid approach: Predictive for hardware/regulatory and Agile for the software interface.
D.
Iterative approach to refine requirements for both hardware and software.
How to approach this question
Analyze the characteristics: Fixed/Stable = Predictive. Uncertain/Evolving = Agile. Both present = Hybrid.
Full Answer
C.Hybrid approach: Predictive for hardware/regulatory and Agile for the software interface.✓ Correct
C
Hybrid methodologies are ideal when a project has mixed characteristics (e.g., tangible industrial components vs. intangible software components).
Common mistakes
Assuming 'medical' always means Predictive or 'software' always means Agile without considering the whole picture.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert