Hard1 markMultiple Choice
PMP · Question 09 · Task 3: Assess and manage risks
A project manager is dealing with two different risks. For Risk A (potential hardware theft), they purchase an insurance policy. For Risk B (potential failure of a new technology), they build a prototype to test feasibility. Which TWO risk response strategies are being used?
A project manager is dealing with two different risks. For Risk A (potential hardware theft), they purchase an insurance policy. For Risk B (potential failure of a new technology), they build a prototype to test feasibility. Which TWO risk response strategies are being used?
Answer options:
A.
Risk A: Avoid
B.
Risk B: Accept
C.
Risk A: Transfer
D.
Risk B: Mitigate
E.
Risk A: Mitigate
F.
Risk B: Avoid
How to approach this question
Match the action to the strategy definition. Insurance = Transfer. Prototyping/Testing = Mitigate.
Full Answer
C,D
Transfer involves shifting responsibility (financial or management) to a third party. Mitigation involves action to reduce probability or impact.
Common mistakes
Thinking insurance 'mitigates' risk (in PM terms, it transfers it).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert