Hard1 markMultiple Choice

PMP · Question 09 · Task 3: Assess and manage risks

A project manager is dealing with two different risks. For Risk A (potential hardware theft), they purchase an insurance policy. For Risk B (potential failure of a new technology), they build a prototype to test feasibility. Which TWO risk response strategies are being used?

Answer options:

A.

Risk A: Avoid

B.

Risk B: Accept

C.

Risk A: Transfer

D.

Risk B: Mitigate

E.

Risk A: Mitigate

F.

Risk B: Avoid

How to approach this question

Match the action to the strategy definition. Insurance = Transfer. Prototyping/Testing = Mitigate.

Full Answer

C,D
Transfer involves shifting responsibility (financial or management) to a third party. Mitigation involves action to reduce probability or impact.

Common mistakes

Thinking insurance 'mitigates' risk (in PM terms, it transfers it).

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam