Domain: Process

Task 3: Assess and manage risks

11 questions across 5 exams

All questions (11)

Q09Hard1 mark·PMI PMP Practice Exam

A project manager is dealing with two different risks. For Risk A (potential hardware theft), they purchase an insurance policy. For Risk B (potential failure of a new technology), they build a prototype to test feasibility. Which TWO risk response strategies are being used?

Worked answer available with free account
View question →
Q46Hard1 mark·PMI PMP Practice Exam

A project manager is using a predictive methodology. During the execution phase, a major supplier goes bankrupt. This risk was identified in the risk register, and the response plan was to use a backup supplier. However, the backup supplier is now charging double the original price. What should the PM do?

Worked answer available with free account
View question →
Q67Hard1 mark·PMI PMP Practice Exam

A project manager is using a 'Risk Burndown Chart'. What is this tool tracking?

Worked answer available with free account
View question →
Q91Medium1 mark·PMI PMP Practice Exam

A project manager is leading a project to develop a new AI algorithm. The project is high risk. The PM decides to use an 'Agile Spike'. What is this?

Worked answer available with free account
View question →

A project manager identifies a risk that a critical vendor might go bankrupt. The project team decides to contract with a secondary vendor to be on standby for a retainer fee. Which risk response strategy is this?

Worked answer available with free account
View question →

During project execution, a team member reports that the server room was flooded due to a burst pipe, destroying the development servers. This event was not identified in the risk register. What should the project manager do FIRST?

Worked answer available with free account
View question →

An agile team is building a fintech application. Regulatory compliance requirements are unclear and evolving. The project manager wants to ensure risks are managed iteratively. Which actions are appropriate? (Select TWO)

Worked answer available with free account
View question →

A project has a 30% chance of a delay costing $20,000 and a 20% chance of a scope reduction saving $10,000. What is the Expected Monetary Value (EMV) of these uncertainties?

Worked answer available with free account
View question →

A project manager is creating a risk management plan for a complex infrastructure project. The sponsor asks why the project manager is spending so much time on this when the project hasn't even started execution. What is the BEST response?

Worked answer available with free account
View question →

A project manager is creating a Risk Management Plan. Which of the following represents the CORRECT sequence of risk processes?

Worked answer available with free account
View question →

An agile team identifies a risk that a new technology might not scale. Which TWO actions represent an appropriate agile risk response?

Worked answer available with free account
View question →

Practice these questions with detailed guidance

Full answers, grading, and explanations on why each answer is correct.