PMP · Question 11 · Task 3: Assess and manage risks
A project manager is creating a Risk Management Plan. Which of the following represents the CORRECT sequence of risk processes?
Answer options:
Identify Risks -> Plan Risk Responses -> Perform Qualitative Analysis -> Monitor Risks
Identify Risks -> Perform Qualitative Analysis -> Perform Quantitative Analysis -> Plan Risk Responses
Plan Risk Management -> Identify Risks -> Plan Risk Responses -> Perform Quantitative Analysis
Identify Risks -> Perform Quantitative Analysis -> Perform Qualitative Analysis -> Plan Risk Responses