    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 11
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksProcessRisk Management

    PMP · Question 11 · Task 3: Assess and manage risks

    A project manager is creating a Risk Management Plan. Which of the following represents the CORRECT sequence of risk processes?

    Answer options:

    A.

    Identify Risks -> Plan Risk Responses -> Perform Qualitative Analysis -> Monitor Risks

    B.

    Identify Risks -> Perform Qualitative Analysis -> Perform Quantitative Analysis -> Plan Risk Responses

    C.

    Plan Risk Management -> Identify Risks -> Plan Risk Responses -> Perform Quantitative Analysis

    D.

    Identify Risks -> Perform Quantitative Analysis -> Perform Qualitative Analysis -> Plan Risk Responses

    How to approach this question

    Remember the funnel: Find them (Identify) -> Sort them (Qualitative) -> Measure them (Quantitative) -> Fix them (Response).

    Full Answer

    B.Identify Risks -> Perform Qualitative Analysis -> Perform Quantitative Analysis -> Plan Risk Responses✓ Correct
    Qualitative analysis is a faster filter to prioritize risks. Quantitative analysis is time-consuming and usually reserved for high-priority risks identified in the Qualitative phase.

    Common mistakes

    Swapping Qualitative and Quantitative analysis.
    Question 10All questionsQuestion 12

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
    View all 20 questions →