Hard1 markMultiple Choice
Task 3: Assess and manage risksProcessRisk Management

PMP · Question 11 · Task 3: Assess and manage risks

A project manager is creating a Risk Management Plan. Which of the following represents the CORRECT sequence of risk processes?

Answer options:

A.

Identify Risks -> Plan Risk Responses -> Perform Qualitative Analysis -> Monitor Risks

B.

Identify Risks -> Perform Qualitative Analysis -> Perform Quantitative Analysis -> Plan Risk Responses

C.

Plan Risk Management -> Identify Risks -> Plan Risk Responses -> Perform Quantitative Analysis

D.

Identify Risks -> Perform Quantitative Analysis -> Perform Qualitative Analysis -> Plan Risk Responses

How to approach this question

Remember the funnel: Find them (Identify) -> Sort them (Qualitative) -> Measure them (Quantitative) -> Fix them (Response).

Full Answer

B.Identify Risks -> Perform Qualitative Analysis -> Perform Quantitative Analysis -> Plan Risk Responses✓ Correct
Identify Risks -> Perform Qualitative Analysis -> Perform Quantitative Analysis -> Plan Risk Responses
Qualitative analysis is a faster filter to prioritize risks. Quantitative analysis is time-consuming and usually reserved for high-priority risks identified in the Qualitative phase.

Common mistakes

Swapping Qualitative and Quantitative analysis.