For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 12
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopeProcessScope ManagementChange Management

    PMP · Question 12 · Task 8: Plan and manage scope

    A stakeholder requests a change to the project scope that will add significant value but will delay the project by three weeks. The project has a strict deadline that cannot be moved. What is the BEST response?

    Answer options:

    A.

    Reject the request immediately citing the fixed deadline.

    B.

    Accept the change and ask the team to work overtime to meet the deadline.

    C.

    Analyze the request to see if other scope items of lower value can be removed (de-scoped) to accommodate the change.

    D.

    Implement the change and update the risk register regarding the schedule delay.

    How to approach this question

    When constraints (Time) are fixed, other variables (Scope) must flex. Look for the trade-off option.

    Full Answer

    C.Analyze the request to see if other scope items of lower value can be removed (de-scoped) to accommodate the change.✓ Correct
    Analyze the request to see if other scope items of lower value can be removed (de-scoped) to accommodate the change.
    To deliver value within a fixed constraint, the PM should look for low-value items to swap out. This preserves the deadline while capturing the new high-value opportunity.

    Common mistakes

    Thinking 'Strict Deadline' means 'No Changes Allowed' (A) rather than 'Trade-offs Required' (C).
    Question 11All questionsQuestion 13

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
    View all 20 questions →