PMP · Question 12 · Task 8: Plan and manage scope
A stakeholder requests a change to the project scope that will add significant value but will delay the project by three weeks. The project has a strict deadline that cannot be moved. What is the BEST response?
Answer options:
Reject the request immediately citing the fixed deadline.
Accept the change and ask the team to work overtime to meet the deadline.
Analyze the request to see if other scope items of lower value can be removed (de-scoped) to accommodate the change.
Implement the change and update the risk register regarding the schedule delay.