Hard1 markMultiple Choice
PMP · Question 17 · Task 3: Assess and manage risks
An agile team identifies a risk that a new technology might not scale. Which TWO actions represent an appropriate agile risk response?
An agile team identifies a risk that a new technology might not scale. Which TWO actions represent an appropriate agile risk response?
Answer options:
A.
Transfer the risk to the client by adding a disclaimer in the contract.
B.
Create a 'Spike' story to prototype and test the technology in the next sprint.
C.
Reprioritize the backlog to address the high-risk feature early (fail fast).
D.
Wait until the end of the project to test scalability when the system is complete.
E.
Increase the contingency reserve by 20%.
How to approach this question
Select active, iterative responses typical of agile (Spikes, Reprioritization).
Full Answer
Spikes gain knowledge. Reprioritization reduces impact by handling it early. Both are proactive.
Common mistakes
Applying predictive risk responses (buffers, transfer) to an agile technical risk.
Practice the full PMI PMP Mini Practice Exam 3
20 questions · hints · full answers · grading
More questions from this exam
Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
Expert