Hard1 markMultiple Choice

PMP · Question 17 · Task 3: Assess and manage risks

An agile team identifies a risk that a new technology might not scale. Which TWO actions represent an appropriate agile risk response?

Answer options:

A.

Transfer the risk to the client by adding a disclaimer in the contract.

B.

Create a 'Spike' story to prototype and test the technology in the next sprint.

C.

Reprioritize the backlog to address the high-risk feature early (fail fast).

D.

Wait until the end of the project to test scalability when the system is complete.

E.

Increase the contingency reserve by 20%.

How to approach this question

Select active, iterative responses typical of agile (Spikes, Reprioritization).

Full Answer

Spikes gain knowledge. Reprioritization reduces impact by handling it early. Both are proactive.

Common mistakes

Applying predictive risk responses (buffers, transfer) to an agile technical risk.