PMP · Question 16 · Task 2: Manage communications
A project manager identifies that a key stakeholder is not reading the weekly status reports, leading to repeated questions about information already communicated. What is the BEST way to address this?
A project manager identifies that a key stakeholder is not reading the weekly status reports, leading to repeated questions about information already communicated. What is the BEST way to address this?
Answer options:
A.
Add a 'read receipt' to the emails to track compliance.
B.
Ask the stakeholder about their preferred communication format and adjust the strategy.
C.
Stop sending the reports and only communicate via meetings.
D.
Escalate to the stakeholder's manager that they are ignoring project communications.
How to approach this question
Focus on the effectiveness of communication, not just the transmission.
Full Answer
B.Ask the stakeholder about their preferred communication format and adjust the strategy.✓ Correct
B
The Communications Management Plan should be updated based on stakeholder feedback and effectiveness.
Common mistakes
Blaming the stakeholder (A, D) instead of adjusting the method.
Practice the full PMI PMP Mini Practice Exam 3
20 questions · hints · full answers · grading
More questions from this exam
Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
Expert