Hard1 markMultiple Choice
PMP · Question 08 · Task 3: Assess and manage risks
A project manager identifies a risk that a critical vendor might go bankrupt. The project team decides to contract with a secondary vendor to be on standby for a retainer fee. Which risk response strategy is this?
A project manager identifies a risk that a critical vendor might go bankrupt. The project team decides to contract with a secondary vendor to be on standby for a retainer fee. Which risk response strategy is this?
Answer options:
A.
Avoid
B.
Mitigate
C.
Transfer
D.
Accept
How to approach this question
Ask: Did we eliminate it (Avoid)? Did we pass it to someone else (Transfer)? Did we reduce prob/impact (Mitigate)? Or did we just wait (Accept)?
Full Answer
B.Mitigate✓ Correct
B
This is mitigation because the action (hiring a standby) reduces the impact of the risk event. It is not transfer because the project still owns the problem of getting the work done.
Common mistakes
Confusing Transfer (insurance/warranties) with Mitigation (reducing impact via redundancy).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert