Hard1 markMultiple Choice
Task 3: Assess and manage risksTask 3RiskMatching Conversion

PMP · Question 08 · Task 3: Assess and manage risks

A project manager identifies a risk that a critical vendor might go bankrupt. The project team decides to contract with a secondary vendor to be on standby for a retainer fee. Which risk response strategy is this?

Answer options:

A.

Avoid

B.

Mitigate

C.

Transfer

D.

Accept

How to approach this question

Ask: Did we eliminate it (Avoid)? Did we pass it to someone else (Transfer)? Did we reduce prob/impact (Mitigate)? Or did we just wait (Accept)?

Full Answer

B.Mitigate✓ Correct
B
This is mitigation because the action (hiring a standby) reduces the impact of the risk event. It is not transfer because the project still owns the problem of getting the work done.

Common mistakes

Confusing Transfer (insurance/warranties) with Mitigation (reducing impact via redundancy).

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam