PMP · Question 09 · Task 3: Assess and manage risks
During project execution, a team member reports that the server room was flooded due to a burst pipe, destroying the development servers. This event was not identified in the risk register. What should the project manager do FIRST?
During project execution, a team member reports that the server room was flooded due to a burst pipe, destroying the development servers. This event was not identified in the risk register. What should the project manager do FIRST?
Answer options:
A.
Update the risk register with the new risk.
B.
Submit a change request to replace the servers.
C.
Log the item in the issue log and implement a workaround.
D.
Use the management reserve to cover the cost of damages.
How to approach this question
Distinguish between a Risk (future/uncertain) and an Issue (present/certain).
Full Answer
C.Log the item in the issue log and implement a workaround.✓ Correct
C
Unidentified risks that occur become issues. The correct process is to record in the issue log and manage the issue. Risk register updates happen later as part of monitoring.
Common mistakes
Updating the risk register for something that has already happened (it belongs in the issue log).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert